top of page
Screenshot 2023-06-13 180949.png
Writer's pictureThe Beagle

Take A Look At What’s Planned Over Coming Months On The Batemans Bay Bridge Replacement Project


Major work on the Batemans Bay Bridge replacement project is continuing, with the project team focused on starting work on a temporary construction jetty south-west of the existing bridge and completing the temporary boat ramp at Korners Park.

A Roads and Maritime Services spokesperson said the NSW Government provided $274 million for the project which will improve freight access, reduce traffic delays in peak periods, and reduce economic and social impacts by removing the current lift span bridge.

“We’re absolutely committed to giving the community plenty of notice of upcoming work to help them plan ahead so they know what to expect,” the spokesperson said.

“Between April and June, major work will include piling and building piers to form the foundation of the new bridge, completing a temporary boat ramp at Korners Park and construction jetty south-west of the existing bridge, and ongoing removal of vegetation and trees in the project area.

“Teams will also complete a new construction facility south of Mogo that will be used throughout the project to manufacture concrete segments of the new bridge.

“There will be changes in traffic conditions on the Princes Highway, between the Kings Highway and North Street, as this work is carried out and the community will be informed before these occur.”

From early May, the car park and boat ramp on the south-west of the existing bridge will be closed to make way for a construction area and temporary jetty for the duration of major work.

This closure will only occur when a temporary boat ramp has been complete at Korners Park to maintain access to the river for boat users.

A temporary jetty will be built on this site and extended into the river to be used to safely move materials on to large barges and cranes the river.

This area will also be used to start land-based piling work from May to form the first foundation of the new bridge.

Temporary public toilets and disabled parking facilities have opened next to the construction area to allow the project team to prepare this area for major work.

For the safety of workers and river users, a marine exclusion zone will also be in place from early May.

The community and nearby residents will be provided more information before these activities start, including work times and impacts.

The community is thanked for its patience as this important work is carried out.

Roads and Maritime looks forward to working with local residents to ensure disruption is kept to a minimum.

Visit rms.nsw.gov.au/BatemansBayBridge for more information on work planned over the next three months.


NOTE: Comments were TRIALED - in the end it failed as humans will be humans and it turned into a pile of merde; only contributed to by just a handful who did little to add to the conversation of the issue at hand. Anyone who would like to contribute an opinion are encouraged to send in a Letter to the Editor where it might be considered for publication

buymeacoffee.png
bottom of page